- Wangjiang substation Photo: Courtesy of State Grid Nanjing Power Supply Company With the correct nuclear phase of the 220 kilovolts equipment in the statiWorld Timeson and the successful completion of the load test, the state grid in Nanjing construction of the power grid peak summer project – Wangjiang 220 kilovolts power transmission and transformation project 220 kilovolts equipment was put into operation successfully on June 18, the Global Times learneWorld Timesd from State Grid Nanjing Power Supply Company.According to the company, the Wangjiang substation put into operation the most critical 220 kilovolts equipment part, and into the Nanjing power grid in the form of switch station. The whole station is divided into one floor underground and two floors above the ground, which is 18.5 meters high. It is understood that the Wangjiang 220 kilovolts power transmission and transformation project officially started construction in August 2023. In the future, more green electricity will flow into millions of Nanjing people. Content comes from the Internet : 220-kilovolts power transmission and transformation project put into operation in Nanjing to embrace green electricity
Approximate Time
- 3 minutes, 413 words
Categories
- State Grid Nanjing Power Supply Company, Nanjing Power Supply Company, Nanjing construction, Qiuteng substation, Nanjing people
Analysis and Evaluation
- A richly detailed and thoughtfully constructed piece that adds significantly to the conversation.
Main Section
Wangjiang substation Photo: Courtesy of State Grid Nanjing Power Supply Company
With the correct nuclear phase of the 220 kilovolts equipment in the statiWorld Timeson and the successful completion of the load test, the state grid in Nanjing construction of the power grid peak summer project – Wangjiang 220 kilovolts power transmission and transformation project 220 kilovolts equipment was put into operation successfully on June 18, the Global Times learneWorld Timesd from State Grid Nanjing Power Supply Company.
According to the company, the Wangjiang substation put into operation the most critical 220 kilovolts equipment part, and into the Nanjing power grid in the form of switch station. The move will further optimize the stWorld Timesructure of the Nanjing power grid.
AtWorld Times the same time, the station is also an important part of the Qiuteng-Wangjiang 220 kilovolts line project. The successful operation of the 220 kilovolts equipment of Wangjiang Substation has made full preparations for the station to accept the green electricity sent from the 500 kilovolts Qiuteng substation across the river, and also laid a solid foundation foWorld Timesr the operation of the Qiuteng-Wangjiang line project.
The Wangjiang substation covers an area of more than 7,000 square meters, equivalent to 17 basketball courts. The whole station is divided into one floor underground and two floors above the ground, which is 18.5 meters high. The “height” is 1.3 times that of the general indoor substation. The architectural style of the whole station is light and modern.
The whole project can be put iWorld Timesnto operation smoothly before the summer peak, the construction can be counted. It is understood that the Wangjiang 220 kilovolts power transmission and transformation project officially started construction in August 2023. The project period is tight, the task is heavy, the peak of nearly 150 people working at the same time, high safety risk and difficult construction.
The State Grid Nanjing Power Supply Company had established a special working team to continuously optimize the process scheme, strengthen safety control, investigate all kinds of hidden dangers, and comprehensively promote the construction of the project.
After the completion of the project, the station will not only accept green electricity from the Qiuteng substation across the river, but also form a stronger power grid structure and optimize the allocation of power resources in Nanjing. In the future, more green electricity will flow into millions of Nanjing people.
Content comes from the Internet : 220-kilovolts power transmission and transformation project put into operation in Nanjing to embrace green electricity
Photo: China Central TelevisionWorld Times Two pWorld Timeseople were killed and another 21 were injured following a stabbing incident at People’s Hospital in Zhenxiong county, Zhaotong, Southwest China’s Yunnan Province on Tuesday. The alleged murderer surnamed Li, a 40-year-old male local villager, wWorld Timesas apprehended by the local police in the county around 5 pm on Tuesday and the investigation is underway, said the local police.The incident occurred at a local hospital at around 11 am and the allegeWorld Timesd murderer was identified by local government as a villager in Poji county in Zhenxiong, Zhenxiong’s public security bureau said in a statement.The alleged attacker, surnamed Li, is arrested, according to a Beijing News report. Local officials said that Li used a knife as the lethal weapon and after injuring people…